| Particulars | Details/Status |
|---|---|
| Project Name | 4-Laning of Ujjain-Badnawar Section of NH-752D from km 26.9 to km 96.00 (Length-69.1 km) in the State of Madhya Pradesh on Hybrid Annuity Mode |
| NH No. (New/old) | NH-752D |
| Scheme/Phase | Bharatmala Pariyojana |
| Mode of Execution | Hybrid Annuity Mode (HAM) |
| Concessionaire Name | M/s GR Ujjain Badnawar Highway Private Limited |
| Date of Letter of Award (LOA) | 24.03.2022 |
| Appointed Date | 10.10.2022 |
| Construction Period (in Days) | 730 Days from the Appointed Date |
| Schedule Completion Date | 08.10.2024 |
| Operation & Maintenance Period | 15 years from COD |
| Authority Name | National Highways Authority of India, PIU-Ujjain |
| Independent Engineer | M/s L. N. Malviya Infra Projects Private Limited, Bhopal |
| Independent Mobilization Date | 17.10.2022 |
| No. of Lanes/ Configuration | 4 Lane |
| Bid Project Cost | 907.00 Cr. |
| Total Length of the Project | 69.100 km |
| No. of Interchanges | 01 no. |
| No. of ROB | 02 nos. |
| No. of Flyovers | 02 nos. |
| No. of Underpasses | VUP-13 no., LVUP-12 nos., SVUP-06 nos. |
| No. of Major Bridges | 04 nos. |
| No. of Minor Bridges | 07 nos. |
| No. of Bypasses (Name of Town, Length) | Ujjain Bypass – 13.580 km Badnagar Bypass – 9.060 km Badnawar Bypass – 5.530 km |
| No. of Culverts | Box Culverts (reconstruction): 08 nos. Box Culverts (new construction): 127 nos. + 5 nos. additional |
| Toll Plaza | 01 no. |