| Component | %Weightage as per Schedule-G | Progress achieved (during current month) | Physical Progress achieved (Cumulative, up to current month) |
|---|---|---|---|
| Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) | 55.10% | 1.31% | 54.10% |
| Major Bridge Works & ROB/ RUB | 12.62% | 0.00% | 12.62% |
| Structures (elevated sections, reinforces earth) | 11.79% | 0.00% | 11.79% |
| Electrical and Public Health Utilities | 4.23% | 0.00% | 4.23% |
| Other Works | 16.26% | 2.15% | 14.96% |
| Total | 100.00% | 3.46% | 97.70% |